Georgia Data Centers
Live tracking of every data center project in Georgia — operational, under construction, announced, and permitted — with developer, tenant, capacity, and supply-chain links.
- Operating: 7
- Operating and expanding: 1
- Under construction: 6
- Announced: 13
- Operating capacity: 1.0 GW
- Pipeline capacity: 8.1 GW
- Grid: Georgia Power (Southern Co.)
Georgia's pipeline is announcement-heavy. Digital Realty's 1.83 GW Project Bunkhouse in Stilesboro and the 900 MW Project Sail from Atlas Development and Prologis in Coweta County are both still on paper, while Microsoft's $24B Fairwater Atlanta campus in Fayetteville is already operating at 859 MW. Georgia Power supplies the grid, and DC BLOX has a 216 MW AI campus under construction in Conyers.
Data Center Index tracks 26 named data center campuses in Georgia (large sites with a source, not every building): 7 operating, 6 under construction, and 13 announced or permitted. The pipeline adds up to 8.1 GW of planned capacity. The grid is operated by Georgia Power (Southern Co.), which runs the interconnection queue. Below: every tracked project in Georgia, ranked by build status, followed by the public companies whose data center revenue is most exposed to this market.
Tracked data center projects in Georgia
- Microsoft Fairwater Atlanta — 859 MW, Fayetteville · operational · developer: QTS · tenant: Microsoft · ~$24.1B
- CoreWeave Dalton 1 & 2 — 40 MW, Dalton · operational · developer: Core Scientific · tenant: CoreWeave · ~$1.1B
- xAI QTS Atlanta — 24 MW, Atlanta · operational · developer: QTS Data Centers · tenant: X Corp / xAI · ~$0.7B
- IBM — Watson AI Data Centers (US) — 100 MW · operational · developer: IBM
- Microsoft Douglasville Campus (East US 3), Douglasville · operational · developer: Microsoft
- Microsoft Palmetto Campus, Palmetto · operational · developer: Microsoft
- Meta Newton Data Center (Stanton Springs), Social Circle · operational · developer: Meta
- QTS Atlanta-Metro Fayetteville Campus, Fayetteville · operational · developer: QTS Data Centers · tenant: Microsoft
- Google LaGrange (Project Pegasus) — 400 MW, LaGrange · under construction · developer: Google · ~$8.0B
- Project Eisenhower / QTS Augusta (Gordon Highway), Augusta · under construction · developer: Eagle South LLC / QTS Data Centers · ~$2.0B
- Microsoft Union City Campus — 324 MW, Union City · under construction · developer: EdgeConneX / TA Realty · tenant: Microsoft · ~$1.8B
- DC BLOX Atlanta West (Douglasville) — 180 MW, Lithia Springs · under construction · developer: DC BLOX · ~$1.2B
- DC BLOX — Conyers AI Campus — 216 MW, Conyers · under construction · developer: DC BLOX
- Equinix xScale Hampton, Hampton · under construction · developer: Equinix
- OpenAI Project Camellia — 3.2 GW, Rincon · announced · developer: OpenAI · ~$20.0B
- Project Ruby (Columbus), Columbus · announced · developer: Habitat Real Estate Partners / Atlas Development · ~$5.2B
- AWS Douglas County (Factory Shoals Road), Douglasville · announced · developer: Amazon Web Services · tenant: AWS · ~$5.0B
- Kingston Technology Hub — 150 MW, Kingston · announced · developer: Thor Acquisition · ~$1.0B
- Microsoft Rome (Project Firecracker), Rome · announced · developer: Microsoft · ~$1.0B
- AWS Butts County, Jackson · announced · developer: Amazon Web Services · tenant: AWS
- Forsyth Technology Campus, Forsyth · permitted · developer: Trammell Crow Company / H&H Timberlands · ~$21.0B
- Newton County Technology Park, Social Circle · permitted · developer: TPA Group · ~$5.0B
- Switch KEEP 2.0 Atlanta North (Cartersville), Cartersville · permitted · developer: Switch · ~$0.8B
- Project Bunkhouse (Taurus, Stilesboro) — 1.8 GW, Stilesboro · permitted · developer: Taurus DC SPE LLC · tenant: Digital Realty
- Atlas Development — Project Sail — 900 MW, Coweta County · permitted · developer: Atlas Development & Prologis
Frequently asked questions
- How many data centers are in Georgia?
- Data Center Index tracks 26 named data center campuses in Georgia as of 2026: 7 operating, 6 under construction, and 13 announced or permitted. Coverage is named campuses with a published source, not every building.
- How much data center capacity does Georgia have?
- 1.0 GW is operating, with 8.1 GW in the announced and under-construction pipeline. 8 of the 13 Georgia campuses carrying a capacity figure show an estimate rather than a figure a named source states, marked "est." on the site.
- What is the largest data center in Georgia?
- OpenAI Project Camellia in Rincon is the largest tracked campus in Georgia at 3.2 GW, developed by OpenAI. That capacity is stated by a named source.
- Who is building data centers in Georgia?
- The most active developers in Georgia by tracked campus count are Microsoft (3 campuses), QTS Data Centers (2 campuses), DC BLOX (2 campuses). Every campus page lists its developer, tenant and the source that names them.
- Which grid operator serves Georgia data centers?
- Georgia Power (Southern Co.) runs the grid and the interconnection queue for Georgia, so new campus power requests are approved on its timeline.
Public companies exposed to Georgia
These public companies have tracked data-center projects in Georgia as developers, tenants, or operators. Use the watchlist to compare them side by side, or click through for capex history and supplier exposure.
- SK Hynix (000660.KS) — chip fab · 1 project in Georgia
- Applied Optoelectronics (AAOI) — networking · 1 project in Georgia
- CoreWeave (CRWV) — gpu cloud · 1 project in Georgia
- Digital Realty (DLR) — dc operator · 1 project in Georgia
- Jacobs Solutions (J) — construction · 1 project in Georgia
- Johnson Controls (JCI) — cooling · 1 project in Georgia
- Modine Manufacturing (MOD) — cooling · 1 project in Georgia
- Microsoft (MSFT) — hyperscaler · 1 project in Georgia
- Micron Technology (MU) — chip fab · 1 project in Georgia
- nVent Electric (NVT) — power equipment · 1 project in Georgia
- OpenAI (OPENAI) — ai lab · 1 project in Georgia
- Schneider Electric (SBGSF) — power equipment · 1 project in Georgia
Other data center markets
Tracked US markets, ranked by pipeline capacity:
- Texas data centers — 55 tracked projects, 63.3 GW pipeline
- Utah data centers — 7 tracked projects, 21.1 GW pipeline
- Pennsylvania data centers — 16 tracked projects, 15.7 GW pipeline
- Ohio data centers — 25 tracked projects, 13.3 GW pipeline
- Virginia data centers — 34 tracked projects, 9.8 GW pipeline
- Kentucky data centers — 8 tracked projects, 8.9 GW pipeline
- Wyoming data centers — 7 tracked projects, 6.1 GW pipeline
- West Virginia data centers — 4 tracked projects, 6.1 GW pipeline
- Florida data centers — 7 tracked projects, 5.9 GW pipeline
- Illinois data centers — 13 tracked projects, 5.5 GW pipeline
- Maryland data centers — 8 tracked projects, 5.3 GW pipeline
- Indiana data centers — 11 tracked projects, 5.0 GW pipeline
- Kansas data centers — 10 tracked projects, 4.5 GW pipeline
- Arizona data centers — 24 tracked projects, 4.4 GW pipeline
- Oklahoma data centers — 12 tracked projects, 4.2 GW pipeline
- North Carolina data centers — 15 tracked projects, 4.1 GW pipeline
- Alabama data centers — 9 tracked projects, 3.4 GW pipeline
- Nebraska data centers — 7 tracked projects, 3.1 GW pipeline
- Louisiana data centers — 8 tracked projects, 3.0 GW pipeline
- Michigan data centers — 9 tracked projects, 2.6 GW pipeline
- Arkansas data centers — 7 tracked projects, 2.5 GW pipeline
- Oregon data centers — 13 tracked projects, 2.5 GW pipeline
- New York data centers — 7 tracked projects, 2.3 GW pipeline
- South Carolina data centers — 8 tracked projects, 1.9 GW pipeline
- Missouri data centers — 6 tracked projects, 1.7 GW pipeline
- Nevada data centers — 10 tracked projects, 1.6 GW pipeline
- Wisconsin data centers — 4 tracked projects, 1.5 GW pipeline
- California data centers — 15 tracked projects, 1.4 GW pipeline
- North Dakota data centers — 4 tracked projects, 1.4 GW pipeline
- Iowa data centers — 8 tracked projects, 1.4 GW pipeline
- Delaware data centers — 1 tracked project, 1.2 GW pipeline
- Montana data centers — 2 tracked projects, 1.1 GW pipeline
- Washington data centers — 5 tracked projects, 1.0 GW pipeline
- Colorado data centers — 4 tracked projects, 800 MW pipeline
- Mississippi data centers — 7 tracked projects, 616 MW pipeline
- Minnesota data centers — 4 tracked projects, 600 MW pipeline
- New Jersey data centers — 3 tracked projects, 550 MW pipeline
- South Dakota data centers — 2 tracked projects, 500 MW pipeline
- Massachusetts data centers — 1 tracked project, 274 MW pipeline
- Idaho data centers — 3 tracked projects, 240 MW pipeline
- Tennessee data centers — 7 tracked projects, 110 MW pipeline
- Connecticut data centers — 1 tracked project, 100 MW pipeline
- New Mexico data centers — 2 tracked projects