Kentucky Data Centers

Live tracking of every data center project in Kentucky (operational, under construction, announced, and permitted) with developer, tenant, capacity, and supply-chain links.

Updated

Each count is a campus: one site, which can hold several buildings. How we count

Rubix plans 2 GW at the former AK Steel works in Russell, the largest of Kentucky's proposed campuses. TeraWulf has announced its 1 GW Muskie campus in Ashland and the 401 MW Justified campus in Hawesville with Anthropic as tenant, and PowerHouse holds a permit for a 400 MW hyperscale campus in southwest Louisville.

Data Center Index tracks 13 named data center campuses in Kentucky (large sites with a source, not every building): 5 operating, 0 under construction, and 8 announced or permitted. The pipeline adds up to 8.3 GW of planned capacity. The grid is operated by MISO, which runs the interconnection queue. Below: every tracked project in Kentucky, ranked by build status, followed by the public companies whose data center revenue is most exposed to this market.

Need Kentucky checked for a deal? A Campus Check covers every campus in your deal or market, up to about 25, with power status and the record behind each figure, in 3 business days for $2,500. A Team licence is $7,500 a year for up to 5 people. See prices.

Tracked data center projects in Kentucky

Frequently asked questions

How many data centers are in Kentucky?
Data Center Index tracks 13 named data center campuses in Kentucky as of 2026: 5 operating, 0 under construction, and 8 announced or permitted. Coverage is named campuses with a published source, not every building.
How much data center capacity does Kentucky have?
160 MW is operating, with 8.3 GW in the announced and under-construction pipeline. Of the 12 Kentucky campuses with a capacity figure, 0 are filed, 6 stated and 6 estimated. Filed means a permit, utility filing or SEC filing states the figure. Stated means the developer or the press states it. Estimated means we modeled or inferred it, and the site marks it "est.". Filed and stated figures carry the date of the newest source behind them.
What is the largest data center in Kentucky?
Rubix Russell Data Center (former AK Steel Ashland Works) in Russell is the largest tracked campus in Kentucky at 2 GW, developed by Rubix Data Centers. That capacity is an estimate. We modeled or inferred it, and no source states it.
Who is building data centers in Kentucky?
The most active developers in Kentucky by tracked campus count are Flexential (2 campuses), PowerHouse Data Centers (2 campuses), TeraWulf (2 campuses). Every campus page lists its developer, tenant and the source that names them.
Which grid operator serves Kentucky data centers?
MISO runs the grid and the interconnection queue for Kentucky, so new campus power requests are approved on its timeline.

Public companies exposed to Kentucky

These public companies have tracked data-center projects in Kentucky as developers, tenants, or operators. Use the watchlist to compare them side by side, or click through for capex history and supplier exposure.

Other data center markets

Tracked US markets, ranked by pipeline capacity: