Oklahoma Data Centers
Live tracking of every data center project in Oklahoma (operational, under construction, announced, and permitted) with developer, tenant, capacity, and supply-chain links.
- Operating: 2
- Operating and expanding: 1
- Under construction: 5
- Announced: 5
- Operating capacity: 1.4 GW
- Pipeline capacity: 4.5 GW
Google anchors Oklahoma: it runs its Pryor campus and is building in Stillwater, Owasso, Summit and Council Hill, while Meta is building in Tulsa. Core Scientific's Muskogee campus for CoreWeave is operating, with 1 GW planned, and the biggest plans are Project Thunderbird in Enid at 2.75 GW and IREN's Project Emerald near Kiowa, which IREN's annual report lists at 1.6 GW of planned power.
Data Center Index tracks 12 named data center campuses in Oklahoma (large sites with a source, not every building): 2 operating, 5 under construction, and 5 announced or permitted. The pipeline adds up to 4.5 GW of planned capacity. Below: every tracked project in Oklahoma, ranked by build status, followed by the public companies whose data center revenue is most exposed to this market.
Tracked data center projects in Oklahoma
- Google Pryor (North), 368 MW, Pryor · operational · developer: Google · tenant: Google DeepMind · ~$13.9B
- Core Scientific Muskogee, 1 GW, Muskogee · operational · developer: Core Scientific · tenant: CoreWeave
- Google / Beale Project Clydesdale, Owasso · under construction · developer: Beale Infrastructure · tenant: Google · ~$3B
- Google Stillwater Campus, Stillwater · under construction · developer: Google · ~$3B
- Meta Tulsa Data Center, Tulsa · under construction · developer: Meta · ~$1B
- Google Summit Campus (Muskogee County), Summit · under construction · developer: Google
- Google Council Hill Campus (Muskogee County), Council Hill · under construction · developer: Google
- IREN Project Emerald (Kiowa), 1.6 GW, Kiowa · announced · developer: IREN · ~$50B
- Project Thunderbird (Enid), 2.8 GW, Enid · announced · developer: Plainsmen Holdings LLC · ~$35B
- CloudBurst Oklahoma City Campus, 200 MW, Oklahoma City · announced · developer: CloudBurst Data Centers
- Beale Project Mustang (Claremore), Claremore · permitted · developer: Beale Infrastructure
- Beltline Energy Oklahoma City / Yukon Campus, Oklahoma City · permitted · developer: Beltline Energy
Frequently asked questions
- How many data centers are in Oklahoma?
- Data Center Index tracks 12 named data center campuses in Oklahoma as of 2026: 2 operating, 5 under construction, and 5 announced or permitted. Coverage is named campuses with a published source, not every building.
- How much data center capacity does Oklahoma have?
- 1.4 GW is operating, with 4.5 GW in the announced and under-construction pipeline. Of the 5 Oklahoma campuses with a capacity figure, 0 are filed, 3 stated and 2 estimated. Filed means a permit, utility filing or SEC filing states the figure. Stated means the developer or the press states it. Estimated means we modeled or inferred it, and the site marks it "est.". Filed and stated figures carry the date of the newest source behind them.
- What is the largest data center in Oklahoma?
- Project Thunderbird (Enid) in Enid is the largest tracked campus in Oklahoma at 2.8 GW, developed by Plainsmen Holdings LLC. The developer or the press states that capacity, in a source dated September 8, 2026.
- Who is building data centers in Oklahoma?
- The most active developers in Oklahoma by tracked campus count are Google (4 campuses), Beale Infrastructure (2 campuses), Core Scientific (1 campus). Every campus page lists its developer, tenant and the source that names them.
Public companies exposed to Oklahoma
These public companies have tracked data-center projects in Oklahoma as developers, tenants, or operators. Use the watchlist to compare them side by side, or click through for capex history and supplier exposure.
- CoreWeave (CRWV), gpu cloud · 1 project in Oklahoma
- Alphabet (GOOGL), hyperscaler · 1 project in Oklahoma
Other data center markets
Tracked US markets, ranked by pipeline capacity:
- Texas data centers, 107 tracked projects, 45.8 GW pipeline
- Utah data centers, 8 tracked projects, 15.6 GW pipeline
- Virginia data centers, 94 tracked projects, 14.4 GW pipeline
- Ohio data centers, 36 tracked projects, 12.2 GW pipeline
- Georgia data centers, 44 tracked projects, 10.4 GW pipeline
- Pennsylvania data centers, 17 tracked projects, 9.2 GW pipeline
- Kentucky data centers, 8 tracked projects, 8.3 GW pipeline
- Kansas data centers, 10 tracked projects, 6.5 GW pipeline
- Illinois data centers, 15 tracked projects, 6.2 GW pipeline
- Florida data centers, 6 tracked projects, 5.6 GW pipeline
- Louisiana data centers, 8 tracked projects, 5.5 GW pipeline
- Wyoming data centers, 8 tracked projects, 5.2 GW pipeline
- West Virginia data centers, 8 tracked projects, 4.9 GW pipeline
- Arizona data centers, 27 tracked projects, 3.7 GW pipeline
- Alabama data centers, 9 tracked projects, 3.4 GW pipeline
- Maryland data centers, 6 tracked projects, 3.2 GW pipeline
- Missouri data centers, 8 tracked projects, 3.2 GW pipeline
- Michigan data centers, 11 tracked projects, 2.5 GW pipeline
- Arkansas data centers, 7 tracked projects, 2.5 GW pipeline
- North Carolina data centers, 16 tracked projects, 2.3 GW pipeline
- Nevada data centers, 12 tracked projects, 1.8 GW pipeline
- North Dakota data centers, 6 tracked projects, 1.7 GW pipeline
- South Carolina data centers, 8 tracked projects, 1.5 GW pipeline
- Indiana data centers, 12 tracked projects, 1.5 GW pipeline
- Oregon data centers, 14 tracked projects, 1.4 GW pipeline
- California data centers, 12 tracked projects, 1.3 GW pipeline
- New York data centers, 4 tracked projects, 1.2 GW pipeline
- Colorado data centers, 5 tracked projects, 1.1 GW pipeline
- Wisconsin data centers, 5 tracked projects, 1.1 GW pipeline
- Montana data centers, 2 tracked projects, 1.1 GW pipeline
- Idaho data centers, 4 tracked projects, 840 MW pipeline
- Mississippi data centers, 7 tracked projects, 728 MW pipeline
- New Jersey data centers, 3 tracked projects, 550 MW pipeline
- South Dakota data centers, 2 tracked projects, 500 MW pipeline
- Nebraska data centers, 7 tracked projects, 403 MW pipeline
- Massachusetts data centers, 1 tracked project, 274 MW pipeline
- Iowa data centers, 8 tracked projects, 261 MW pipeline
- Minnesota data centers, 5 tracked projects, 178 MW pipeline
- Connecticut data centers, 1 tracked project, 100 MW pipeline
- Tennessee data centers, 8 tracked projects, 10 MW pipeline
- Maine data centers, 1 tracked project
- New Mexico data centers, 2 tracked projects
- Washington data centers, 5 tracked projects