CoreWeave Dalton 1 & 2

28 MW AI data center in Dalton, GA, United States: operational.

CoreWeave Dalton 1 & 2 is a 28 MW AI data center project located in Dalton, GA, United States, currently operational. It is being built by Core Scientific for tenant CoreWeave. The estimated build cost is $1.1B. This project is one of thousands of data-center facilities tracked by Data Center Index across GA, United States, covering operational, under-construction, announced, and permitted sites.

Notes

Users: OpenAI; Epoch 'Current power' = 28 MW (may include campus expansions); Cost modeled at ~$44B/GW by Epoch AI

Public companies linked to CoreWeave Dalton 1 & 2

Developers, tenants, and suppliers tracked by Data Center Index with exposure to this project:

Related data center projects

Frequently asked questions

What is CoreWeave Dalton 1 & 2?
CoreWeave Dalton 1 & 2 is an AI data center project in Dalton, Georgia tracked by Data Center Index. Its status is operational.
Where is CoreWeave Dalton 1 & 2?
CoreWeave Dalton 1 & 2 is in Dalton, Georgia. Every tracked Georgia campus, with counts and capacity, is at https://datacenterindex.ai/markets/georgia.
How big is CoreWeave Dalton 1 & 2?
Data Center Index tracks CoreWeave Dalton 1 & 2 at 28 MW, on an estimated $1.1B build. That capacity is an estimate. We modeled or inferred it, and no source states it.
Who is building CoreWeave Dalton 1 & 2?
Core Scientific is developing CoreWeave Dalton 1 & 2, with CoreWeave named as the tenant.
Which public companies are linked to CoreWeave Dalton 1 & 2?
Data Center Index links 1 tracked public company to CoreWeave Dalton 1 & 2: CoreWeave (CRWV). Each is a developer, tenant or supplier with a sourced link to the project.

Sources

  1. Dalton Daily Citizen (daltoncitizen.com · press · 2026-05-30)
  2. CoreWeave Dalton 1 & 2 | AI Data Centers (epoch.ai · aggregator · 2026-09-11)
  3. Core Scientific (corescientific.com · press · 2025-03-24)