Microsoft Fairwater Atlanta
859 MW AI data center in Fayetteville, GA, United States — operational.
- Capacity: 859 MW
- Location: Fayetteville, GA, United States
- Developer: Microsoft
- Tenant: OpenAI
- Status: operational
- Estimated cost: $23.5B
- Energy source: Grid (We Energies) + 250MW Solar PPA
Microsoft Fairwater Atlanta is a 859 MW AI data center project located in Fayetteville, GA, United States, currently operational. It is being built by Microsoft for tenant OpenAI. The estimated build cost is $23.5B. Power for the facility is sourced from Grid (We Energies) + 250MW Solar PPA. This project is one of thousands of data-center facilities tracked by Data Center Index across GA, United States — covering operational, under-construction, announced, and permitted sites.
Notes
Users: OpenAI, Microsoft; Epoch 'Current power' = 859 MW (may include campus expansions); Cost modeled at ~$44B/GW by Epoch AI
Linked public companies
- Microsoft (MSFT) — developer
- Microsoft (MSFT) — tenant
- OpenAI (OPENAI) — tenant
- Schneider Electric (SBGSF) — transformer ups
- Johnson Controls (JCI) — hvac
- Jacobs Solutions (J) — engineering
- Micron Technology (MU) — memory supplier
- SK Hynix (000660.KS) — memory supplier
- Modine Manufacturing (MOD) — liquid cooling
- nVent Electric (NVT) — enclosures cooling
- Applied Optoelectronics (AAOI) — optical transceiver