Project Red Clay
1.5 GW AI data center in Burkville, AL, United States: announced.
- Capacity: 1.5 GW
- Location: Burkville, AL, United States
- Developer: Cloverleaf Infrastructure
- Status: announced
- Estimated cost: $1.5B
Project Red Clay is a 1.5 GW AI data center project located in Burkville, AL, United States, currently announced. It is being built by Cloverleaf Infrastructure. The estimated build cost is $1.5B. This project is one of thousands of data-center facilities tracked by Data Center Index across AL, United States, covering operational, under-construction, announced, and permitted sites.
Project description
Project Red Clay is an 800-acre data center in Lowndes County near Hayneville that has requested 1,500 megawatts of capacity from Alabama Power. It's estimated to cost at least $1.5 billion in the development stage. Cloverleaf owns the project LLC, and developers said an agreement identifying the operator hasn't been finalized.
Related data center projects
- Cloverleaf Project Bluestem (Tonganoxie), 1.2 GW, Tonganoxie, KS, United States · announced
- Pumpkin Technology Campus, Harlem, GA, United States · permitted
- PORTS-Pike Technology Campus, 8 GW, Piketon, OH, United States · announced
- Nexus Hubbard Campus, 7.7 GW, Hubbard, TX, United States · under construction
- Stratos Hyperscale Data Center, 7.5 GW, Snowville, UT, United States · announced
- Meta Hyperion, 5 GW, Holly Ridge, LA, United States · under construction
- Data City Texas, 5 GW, Laredo, TX, United States · announced
- Creekstone Delta Gigasite, 4.6 GW, Delta, UT, United States · under construction
Frequently asked questions
- What is Project Red Clay?
- Project Red Clay is an AI data center project in Burkville, Alabama tracked by Data Center Index. Its status is announced.
- Where is Project Red Clay?
- Project Red Clay is in Burkville, Alabama. Every tracked Alabama campus, with counts and capacity, is at https://datacenterindex.ai/markets/alabama.
- How big is Project Red Clay?
- Data Center Index tracks Project Red Clay at 1.5 GW, on an estimated $1.5B build. That capacity is an estimate. We modeled or inferred it, and no source states it.
- Who is building Project Red Clay?
- Cloverleaf Infrastructure is developing Project Red Clay.
Sources
- Lowndes County residents demand transparency in hyperscale data center development (yahoo.com · press · 2026-08-25)
- Route Fifty (syndicating Alabama Reflector) (route-fifty.com · press · 2026-08-25)
- WBHM (wbhm.org · press · 2026-10-07)
- Data Center Gets Massive Tax Break in Surprise Vote by Lowndes Commission (selc.org · press · 2026-10-14)
- NRDC (nrdc.org · press · 2026-10-14)
- Yellowhammer News (yellowhammernews.com · press · 2026-08-25)