Fluidstack Abernathy

168 MW AI data center in Abernathy, TX, United States: under construction.

Fluidstack Abernathy is a 168 MW AI data center project located in Abernathy, TX, United States, currently under construction. It is being built by Fluidstack. This project is one of thousands of data-center facilities tracked by Data Center Index across TX, United States, covering operational, under-construction, announced, and permitted sites.

Project description

TeraWulf sold its 50.1% stake in the Abernathy JV, a 168 MW critical IT site, to a group led by Fluidstack. The sale monetizes about $450M of invested capital, and the site is described as under development.

Related data center projects

Frequently asked questions

What is Fluidstack Abernathy?
Fluidstack Abernathy is an AI data center project in Abernathy, Texas tracked by Data Center Index. Its status is under construction.
Where is Fluidstack Abernathy?
Fluidstack Abernathy is in Abernathy, Texas. Every tracked Texas campus, with counts and capacity, is at https://datacenterindex.ai/markets/texas.
How big is Fluidstack Abernathy?
Data Center Index tracks Fluidstack Abernathy at 168 MW. The developer or the press states that capacity, in a source dated October 7, 2026.
Who is building Fluidstack Abernathy?
Fluidstack is developing Fluidstack Abernathy.

Sources

  1. TeraWulf Announces Anthropic Lease at Justified Data Campus and Sale of Majority Interest in Abernathy Joint Venture to Fluidstack (investors.terawulf.com · press · 2026-07-06)
  2. SEC EDGAR (TeraWulf 8-K EX-99.1) (sec.gov · filing · 2025-10-28)
  3. TeraWulf (investors.terawulf.com · press · 2025-12-18)