100 MW AI data center in Forest Grove, OR, United States: under construction.

Crane PDX01 (Forest Grove) is a 100 MW AI data center project located in Forest Grove, OR, United States, currently under construction. It is being built by Crane Data Centers. This project is one of thousands of data-center facilities tracked by Data Center Index across OR, United States, covering operational, under-construction, announced, and permitted sites.

Project description

Fortis is building Crane's PDX01 campus in Forest Grove, ready for service in 2026. The first phase is 24 MW with 36,000 sq ft of white space, and the total campus is planned at 100+ MW.

Related data center projects

Frequently asked questions

What is Crane PDX01 (Forest Grove)?
Crane PDX01 (Forest Grove) is an AI data center project in Forest Grove, Oregon tracked by Data Center Index. Its status is under construction.
Where is Crane PDX01 (Forest Grove)?
Crane PDX01 (Forest Grove) is in Forest Grove, Oregon. Every tracked Oregon campus, with counts and capacity, is at https://datacenterindex.ai/markets/oregon.
How big is Crane PDX01 (Forest Grove)?
Data Center Index tracks Crane PDX01 (Forest Grove) at 100 MW. That capacity is an estimate. We modeled or inferred it, and no source states it.
Who is building Crane PDX01 (Forest Grove)?
Crane Data Centers is developing Crane PDX01 (Forest Grove).
When will Crane PDX01 (Forest Grove) come online?
The next building at Crane PDX01 (Forest Grove) is expected online 2027. That date is the first building going live, not the full build-out.

Sources

  1. Crane, PDX01 Data Center Campus | Fortis Construction (fortisconstruction.com · press · 2025-07-10)
  2. Construction Review Online (constructionreviewonline.com · press · 2025-07-26)
  3. jhkelly.com (press · 2026-04-07)