TerraWatt St. Louis Armory Data Center

120 MW AI data center in St. Louis, MO, United States: permitted.

TerraWatt St. Louis Armory Data Center is a 120 MW AI data center project located in St. Louis, MO, United States, currently permitted. It is being built by TerraWatt. The estimated build cost is $3B. This project is one of thousands of data-center facilities tracked by Data Center Index across MO, United States, covering operational, under-construction, announced, and permitted sites.

Project description

St. Louis's Land Clearance for Redevelopment Authority gave final approval to a community benefit plan with TerraWatt for its planned 120 MW, $3 billion data center at the former Famous-Barr building at 3728 Market St.; construction is expected to begin in August 2027 and finish by late 2029. Conditional use permits were approved in April 2026.

Related data center projects

Frequently asked questions

What is TerraWatt St. Louis Armory Data Center?
TerraWatt St. Louis Armory Data Center is an AI data center project in St. Louis, Missouri tracked by Data Center Index. Its status is permitted.
Where is TerraWatt St. Louis Armory Data Center?
TerraWatt St. Louis Armory Data Center is in St. Louis, Missouri. Every tracked Missouri campus, with counts and capacity, is at https://datacenterindex.ai/markets/missouri.
How big is TerraWatt St. Louis Armory Data Center?
Data Center Index tracks TerraWatt St. Louis Armory Data Center at 120 MW, on an estimated $3B build. The developer or the press states that capacity, in a source dated September 15, 2026.
Who is building TerraWatt St. Louis Armory Data Center?
TerraWatt is developing TerraWatt St. Louis Armory Data Center.
When will TerraWatt St. Louis Armory Data Center come online?
The next building at TerraWatt St. Louis Armory Data Center is expected online 2029. That date is the first building going live, not the full build-out.

Sources

  1. St. Louis okays Midtown data center (stlpr.org · press · 2026-09-15)