Applied Digital Polaris Forge 2 (Harwood)
300 MW AI data center in Harwood, ND, United States: under construction.
- Capacity: 300 MW
- Location: Harwood, ND, United States
- Developer: Applied Digital
- Tenant: Oracle
- Status: under construction
- Estimated cost: $3B
Applied Digital Polaris Forge 2 (Harwood) is a 300 MW AI data center project located in Harwood, ND, United States, currently under construction. It is being built by Applied Digital for tenant Oracle. The estimated build cost is $3B. This project is one of thousands of data-center facilities tracked by Data Center Index across ND, United States, covering operational, under-construction, announced, and permitted sites.
Project description
Applied Digital is building Polaris Forge 2, an AI Factory campus on 900+ contracted acres near Harwood, north of Fargo. Its two buildings total 300 MW, leased to an investment-grade hyperscaler, with initial ready for service expected in the second half of 2026 and full capacity in early 2027.
Related data center projects
- Applied Digital Deuel County Campus (Toronto), 430 MW, Toronto, SD, United States · cancelled
- Applied Digital Polaris Forge 1 (Ellendale), 400 MW, Ellendale, ND, United States · operational
- Applied Digital Delta Forge 1, 300 MW, Boyce, LA, United States · under construction
- Applied Digital Polaris Forge 3, 300 MW, Center, ND, United States · under construction
- Applied Digital Brookwood, 210 MW, Brookwood, AL, United States · permitted
- Applied Digital Garden City, 200 MW, Garden City, TX, United States · operational
- Applied Digital Ellendale Hosting Facility, 180 MW, Ellendale, ND, United States · operational
- Applied Digital Jamestown Hosting Facility, 106 MW, Jamestown, ND, United States · operational
Frequently asked questions
- What is Applied Digital Polaris Forge 2 (Harwood)?
- Applied Digital Polaris Forge 2 (Harwood) is an AI data center project in Harwood, North Dakota tracked by Data Center Index. Its status is under construction.
- Where is Applied Digital Polaris Forge 2 (Harwood)?
- Applied Digital Polaris Forge 2 (Harwood) is in Harwood, North Dakota. Every tracked North Dakota campus, with counts and capacity, is at https://datacenterindex.ai/markets/north-dakota.
- How big is Applied Digital Polaris Forge 2 (Harwood)?
- Data Center Index tracks Applied Digital Polaris Forge 2 (Harwood) at 300 MW, on an estimated $3B build. A permit, utility filing or SEC filing states that capacity, in a source dated October 7, 2026.
- Who is building Applied Digital Polaris Forge 2 (Harwood)?
- Applied Digital is developing Applied Digital Polaris Forge 2 (Harwood), with Oracle named as the tenant.
Sources
- Applied Digital to Break Ground on $3 Billion Polaris Forge 2 Campus in September 2025 (ir.applieddigital.com · press · 2025-08-18)
- Montana-Dakota Utilities Announces Electric Service Agreement with Applied Digital for Proposed AI Factory (prnewswire.com · press · 2026-06-22)
- InForum (Fargo) (inforum.com · press · 2026-09-12)
- BIC Magazine (bicmagazine.com · press · 2026-10-07)
- Applied Digital Form 10-Q, quarter ended August 31, 2026 (sec.gov · filing · 2026-10-07)
- Applied Digital Form 8-K, March 4, 2026 (sec.gov · filing · 2026-03-04)
- Valley News Live (valleynewslive.com · press · 2026-09-12)