Aligned Pataskala Data Center

200 MW AI data center in Pataskala, OH, United States: paused.

Status: Paused

City council denied the site plan on August 25, 2026; a paused status follows as a correction. Source: NBC4 WCMH-TV, 2026-08-25.

Paused and cancelled projects stay listed in the directory but are not counted in state totals, capacity totals or rankings.

Aligned Pataskala Data Center is a 200 MW AI data center project located in Pataskala, OH, United States, currently paused. It was being developed by Aligned Data Centers. This project is one of thousands of data-center facilities tracked by Data Center Index across OH, United States, covering operational, under-construction, announced, and permitted sites.

Project description

Aligned Data Centers proposed a 200 megawatt data center in three buildings on an 89 acre parcel at Broad and Mink streets in Pataskala's industrial park.

Related data center projects

Frequently asked questions

What is Aligned Pataskala Data Center?
Aligned Pataskala Data Center is an AI data center project in Pataskala, Ohio tracked by Data Center Index. Its status is paused. A paused campus stays listed with its source, but is never counted in state totals, capacity totals or rankings.
Where is Aligned Pataskala Data Center?
Aligned Pataskala Data Center is in Pataskala, Ohio. Every tracked Ohio campus, with counts and capacity, is at https://datacenterindex.ai/markets/ohio.
How big is Aligned Pataskala Data Center?
Data Center Index tracks Aligned Pataskala Data Center at 200 MW. The developer or the press states that capacity, in a source dated June 30, 2026.
Who is building Aligned Pataskala Data Center?
Aligned Data Centers was developing Aligned Pataskala Data Center.

Sources

  1. Should Pataskala allow data center in industrial park? Council sets hearing (aol.com · press · 2026-06-30)
  2. NBC4 WCMH-TV (nbc4i.com · press · 2026-08-25)