Vantage Frankfurt I Campus (Offenbach)

55 MW AI data center in Offenbach am Main, Germany: operational.

Vantage Frankfurt I Campus (Offenbach) is a 55 MW AI data center project located in Offenbach am Main, Germany, currently operational. It is being built by Vantage Data Centers. This project is one of thousands of data-center facilities tracked by Data Center Index across Germany, covering operational, under-construction, announced, and permitted sites.

Project description

Vantage opened the first 15 MW data center on its 55 MW Frankfurt I campus in Offenbach in November 2020 with EVO and DataCenter-Group, and is continuing to develop the campus.

Related data center projects

Frequently asked questions

What is Vantage Frankfurt I Campus (Offenbach)?
Vantage Frankfurt I Campus (Offenbach) is an AI data center project in Offenbach am Main, Germany tracked by Data Center Index. Its status is operational.
Where is Vantage Frankfurt I Campus (Offenbach)?
Vantage Frankfurt I Campus (Offenbach) is in Offenbach am Main, Germany.
How big is Vantage Frankfurt I Campus (Offenbach)?
Data Center Index tracks Vantage Frankfurt I Campus (Offenbach) at 55 MW. The developer or the press states that capacity, in a source dated November 3, 2022.
Who is building Vantage Frankfurt I Campus (Offenbach)?
Vantage Data Centers is developing Vantage Frankfurt I Campus (Offenbach).

Sources

  1. Vantage Data Centers Opens Three New Facilities in Berlin and Frankfurt, Establishes Office in Raunheim, Germany (vantage-dc.com · press · 2022-11-03)
  2. Vantage Data Centers (vantage-dc.com · press · 2022-11-03)