Project Washington (Starwood Delaware City Campus)

1.2 GW AI data center in Delaware City, DE, United States: paused.

Status: Paused

Paused: Delaware's Environmental Secretary ruled the design violates the Coastal Zone Act (516 backup diesel generators, 2.5 million gallons of diesel), and Starwood withdrew its Superior Court appeal in early July 2026, so the project cannot proceed under its current design (Spotlight Delaware, August 28, 2026). Starwood says it is working with regulators and the community to find a pathway forward. Site Selection cites 432 MW IT per phase (864 MW total). The $10 billion cost is Starwood's total investment figure from its July 2025 town hall presentation (Spotlight Delaware, July 25, 2025); in October 2025 Spotlight Delaware reported company officials saying the facility could be worth $7 billion, and Site Selection's $9.7 billion figure is projected economic output. The site is two New Castle County tax parcels off Hamburg Road, River Road and Governor Lea Road near Delaware City, per the Delaware Department of Natural Resources and Environmental Control's February 2026 Coastal Zone Act status decision; it is outside the City of New Castle. Source: Spotlight Delaware, 2026-08-28.

Paused and cancelled projects stay listed in the directory but are not counted in state totals, capacity totals or rankings.

Project Washington (Starwood Delaware City Campus) is a 1.2 GW AI data center project located in Delaware City, DE, United States, currently paused. It was being developed by Starwood Digital Ventures. The estimated build cost is $10B. This project is one of thousands of data-center facilities tracked by Data Center Index across DE, United States, covering operational, under-construction, announced, and permitted sites.

Project description

Starwood Digital Ventures filed two applications with New Castle County for an 11-building, 1.2 GW campus of 6 million sq ft on about 580 acres of PBF Energy land near Delaware City. Power would come from Delmarva's Red Lion substation. Construction was targeted for Q3 2026, with initial operations in Q2 2028.

Related data center projects

Frequently asked questions

What is Project Washington (Starwood Delaware City Campus)?
Project Washington (Starwood Delaware City Campus) is an AI data center project in Delaware City, Delaware tracked by Data Center Index. Its status is paused. A paused campus stays listed with its source, but is never counted in state totals, capacity totals or rankings.
Where is Project Washington (Starwood Delaware City Campus)?
Project Washington (Starwood Delaware City Campus) is in Delaware City, Delaware. Every tracked Delaware campus, with counts and capacity, is at https://datacenterindex.ai/markets/delaware.
How big is Project Washington (Starwood Delaware City Campus)?
Data Center Index tracks Project Washington (Starwood Delaware City Campus) at 1.2 GW, on an estimated $10B build. That capacity is an estimate. We modeled or inferred it, and no source states it.
Who is building Project Washington (Starwood Delaware City Campus)?
Starwood Digital Ventures was developing Project Washington (Starwood Delaware City Campus).

Sources

  1. Starwood files to develop 1.2GW, 11-building data center campus in Delaware (datacenterdynamics.com · press · 2025-07-11)
  2. Spotlight Delaware (spotlightdelaware.org · press · 2026-08-28)
  3. WHYY (whyy.org · press · 2026-02-05)
  4. WDEL (wdel.com · press · 2026-10-07)
  5. Site Selection (siteselection.com · press · 2025-11-10)
  6. Delaware DNREC (via Spotlight Delaware) (spotlightdelaware.org · press · 2026-02-01)
  7. Spotlight Delaware (spotlightdelaware.org · press · 2025-07-25)
  8. Delaware Business Now (delawarebusinessnow.com · press · 2026-08-28)
  9. Spotlight Delaware (spotlightdelaware.org · press · 2025-11-10)