350 MW AI data center in Middleton Township (Bowling Green), OH, United States — under construction.

Meta Bowling Green Data Center is a 350 MW AI data center project located in Middleton Township (Bowling Green), OH, United States, currently under construction. It is being built by Meta. The estimated build cost is $0.8B. This project is one of thousands of data-center facilities tracked by Data Center Index across OH, United States — covering operational, under-construction, announced, and permitted sites.

Project description

Meta's $800M data center is under construction in Middleton Township about five miles north of Bowling Green with roughly 1,000 construction workers on site, ~100 operational jobs planned, $28M in road/water infrastructure and a Meta-built 2 million gallon water tank.