Adams Fork Data Energy Center
AI data center in Wharncliffe, WV, United States: announced.
- Location: Wharncliffe, WV, United States
- Developer: TransGas Development Systems
- Status: announced
Adams Fork Data Energy Center is a AI data center project located in Wharncliffe, WV, United States, currently announced. It is being built by TransGas Development Systems. This project is one of thousands of data-center facilities tracked by Data Center Index across WV, United States, covering operational, under-construction, announced, and permitted sites.
Project description
TransGas filed air permit applications for off-grid gas power plants to supply two planned data centers, one at 2002 Twisted Gun Road in Wharncliffe; each power facility would have aggregate output of 2,457 MW, with anticipated startup Jan. 1, 2027.
Related data center projects
- Adams Fork Harless Data Center Energy Campus, Holden, WV, United States · announced
- Stratos Hyperscale Data Center, 9 GW, Hansel Valley, UT, United States · announced
- PORTS-Pike Technology Campus, 8 GW, Piketon, OH, United States · under construction
- Nexus Hubbard Campus, 7.7 GW, Hubbard, TX, United States · under construction
- Meta Hyperion, 5 GW, Holly Ridge, LA, United States · under construction
- Data City Texas, 5 GW, Laredo, TX, United States · announced
- Creekstone Delta Gigasite, 4.6 GW, Delta, UT, United States · under construction
- Tract Caldwell Valley Technology Park, 4 GW, Uhland, TX, United States · announced
Frequently asked questions
- What is Adams Fork Data Energy Center?
- Adams Fork Data Energy Center is an AI data center project in Wharncliffe, West Virginia tracked by Data Center Index. Its status is announced.
- Where is Adams Fork Data Energy Center?
- Adams Fork Data Energy Center is in Wharncliffe, West Virginia. Every tracked West Virginia campus, with counts and capacity, is at https://datacenterindex.ai/markets/west-virginia.
- Who is building Adams Fork Data Energy Center?
- TransGas Development Systems is developing Adams Fork Data Energy Center.
Sources
- DEP sets in-person meeting on Mingo data center permit plans after public outcry (wvgazettemail.com · press · 2025-08-29)