Canada Data Centers
Live tracking of every data center project in Canada (operational, under construction, announced, and permitted) with developer, tenant, capacity, and supply-chain links.
- Operating: 1
- Operating and expanding: 1
- Under construction: 2
- Announced: 1
- Operating capacity: 27 MW
- Pipeline capacity: 7.7 GW
Data Center Index tracks 4 named data center campuses in Canada (large sites with a source, not every building): 1 operating, 2 under construction, and 1 announced or permitted. The pipeline adds up to 7.7 GW of planned capacity. Below: every tracked project in Canada, ranked by build status, followed by the public companies whose data center revenue is most exposed to this market.
Tracked data center projects in Canada
- Vantage Data Centers Quebec Expansion (Montreal & Quebec City), 178 MW, Montreal · operational · developer: Vantage Data Centers
- Amazon Web Services Canada West Region (Calgary), 80 MW, Calgary · operational · developer: Amazon Web Services
- Yondr Toronto AI Data Center, 27 MW, Toronto · operational · developer: Yondr Group
- Bell AI Fabric Data Center Network (British Columbia), 500 MW, Kamloops & Merritt · under construction · developer: Bell Canada (BCE)
- Microsoft Markham AI Megaproject, 112 MW, Markham · under construction · developer: Microsoft
- eStruxture's CAL-3 Hyperscale Data Center (Calgary), 90 MW, Balzac · under construction · developer: eStruxture Data Centres
- Wonder Valley Off-Grid AI Data Center Park, 7.5 GW, Grande Prairie · announced · developer: O'Leary Digital
- Beacon AI Alberta Hyperscale Campuses, 4.5 GW, Calgary & Edmonton Areas · announced · developer: Beacon AI Centers
Frequently asked questions
- How many data centers are in Canada?
- Data Center Index tracks 4 named data center campuses in Canada as of 2026: 1 operating, 2 under construction, and 1 announced or permitted. Coverage is named campuses with a published source, not every building.
- How much data center capacity does Canada have?
- 27 MW is operating, with 7.7 GW in the announced and under-construction pipeline. Of the 8 Canada campuses with a capacity figure, 0 are filed, 3 stated and 5 estimated. Filed means a permit, utility filing or SEC filing states the figure. Stated means the developer or the press states it. Estimated means we modeled or inferred it, and the site marks it "est.". Filed and stated figures carry the date of the newest source behind them.
- What is the largest data center in Canada?
- Wonder Valley Off-Grid AI Data Center Park in Grande Prairie is the largest tracked campus in Canada at 7.5 GW, developed by O'Leary Digital. That capacity is an estimate. We modeled or inferred it, and no source states it.
- Who is building data centers in Canada?
- Developers with a tracked campus in Canada include Vantage Data Centers, Amazon Web Services, Yondr Group. Every campus page lists its developer, tenant and the source that names them.
Public companies exposed to Canada
These public companies have tracked data-center projects in Canada as developers, tenants, or operators. Use the watchlist to compare them side by side, or click through for capex history and supplier exposure.
- Amazon (AMZN), hyperscaler · 1 project in Canada
- Microsoft (MSFT), hyperscaler · 1 project in Canada
- Vantage Data Centers (VANTAGE), dc operator · 1 project in Canada
Other data center markets
Other tracked countries, ranked by pipeline capacity:
- China data centers, 9 tracked projects
- France data centers, 7 tracked projects, 2.5 GW pipeline
- Germany data centers, 6 tracked projects, 120 MW pipeline
- Japan data centers, 5 tracked projects, 750 MW pipeline
- Australia data centers, 5 tracked projects, 673 MW pipeline
- Norway data centers, 5 tracked projects, 470 MW pipeline
- South Korea data centers, 4 tracked projects, 4.0 GW pipeline
- India data centers, 4 tracked projects, 1.6 GW pipeline
- Thailand data centers, 4 tracked projects, 792 MW pipeline
- Finland data centers, 4 tracked projects, 430 MW pipeline