NTT Berlin Data Center (36 MW)

36 MW AI data center in Berlin, Germany: under construction.

NTT Berlin Data Center (36 MW) is a 36 MW AI data center project located in Berlin, Germany, currently under construction. It is being built by NTT Global Data Centers. This project is one of thousands of data-center facilities tracked by Data Center Index across Germany, covering operational, under-construction, announced, and permitted sites.

Project description

HOCHTIEF and Turner (Dornan) won the contract to build a 36 MW NTT data center and office building in Berlin; construction began in June 2026, the first data halls are due in 2028 and full completion in 2029.

Related data center projects

Frequently asked questions

What is NTT Berlin Data Center (36 MW)?
NTT Berlin Data Center (36 MW) is an AI data center project in Berlin, Germany tracked by Data Center Index. Its status is under construction.
Where is NTT Berlin Data Center (36 MW)?
NTT Berlin Data Center (36 MW) is in Berlin, Germany.
How big is NTT Berlin Data Center (36 MW)?
Data Center Index tracks NTT Berlin Data Center (36 MW) at 36 MW. That capacity is an estimate. We modeled or inferred it, and no source states it.
Who is building NTT Berlin Data Center (36 MW)?
NTT Global Data Centers is developing NTT Berlin Data Center (36 MW).
When will NTT Berlin Data Center (36 MW) come online?
The next building at NTT Berlin Data Center (36 MW) is expected online 2028. That date is the first building going live, not the full build-out.

Sources

  1. HOCHTIEF wins contract to build a data center for NTT in Berlin (hochtief.com · press · 2026-07-07)
  2. Construction Owners (constructionowners.com · press · 2026-07-07)