T5 Data Centers
Tracked AI data center portfolio for T5 Data Centers: live capex history, supplier exposure, and project map.
- Projects tracked: 3
- Total pipeline: 1.3 GW
Projects
- T5 @ Chicago IV (Grayslake), 1.2 GW, Grayslake, IL, United States · under construction
- T5 Chantilly Fuel Cell Data Center, 60 MW, Chantilly, VA, United States · announced
- T5 Coweta Campus (Project Pegasus), Palmetto, GA, United States · announced
Frequently asked questions
- How many data centers does T5 Data Centers have?
- Data Center Index tracks 3 data center campuses with T5 Data Centers named as the developer or the tenant. Coverage is named campuses with a published source, not every building.
- How much data center capacity does T5 Data Centers have?
- 1.3 GW across 3 tracked campuses, counting operating and pipeline sites together. Of the 2 T5 Data Centers campuses with a capacity figure, 0 are filed, 1 stated and 1 estimated. Filed means a permit, utility filing or SEC filing states the figure. Stated means the developer or the press states it. Estimated means we modeled or inferred it, and the site marks it "est.".
- Where does T5 Data Centers build data centers?
- Tracked T5 Data Centers campuses sit in 3 markets: GA (1), IL (1), VA (1). The figure in brackets is how many campuses Data Center Index tracks in each.
- What is the largest T5 Data Centers data center?
- T5 @ Chicago IV (Grayslake) in IL is the largest tracked T5 Data Centers campus at 1.2 GW, currently under construction. The developer or the press states that capacity, in a source dated September 22, 2026.